{ "cpm": { "duration_workdays": 12, "finish_date": "2025-06-17", "critical_path": ["A", "C", "E", "F", "G"], "tasks": [ {"task_id": "A", "early_start": "2025-06-02", "early_finish": "2025-06-03", "total_float_workdays": 0}, {"task_id": "B", "early_start": "2025-06-04", "early_finish": "2025-06-06", "total_float_workdays": 1}, {"task_id": "C", "early_start": "2025-06-04", "early_finish": "2025-06-09", "total_float_workdays": 0}, {"task_id": "D", "early_start": "2025-06-04", "early_finish": "2025-06-05", "total_float_workdays": 5}, {"task_id": "E", "early_start": "2025-06-10", "early_finish": "2025-06-12", "total_float_workdays": 0}, {"task_id": "F", "early_start": "2025-06-13", "early_finish": "2025-06-16", "total_float_workdays": 0}, {"task_id": "G", "early_start": "2025-06-17", "early_finish": "2025-06-17", "total_float_workdays": 0} ] }, "resource_conflicts": [ {"resource": "周启", "tasks": ["B", "D"], "overlap_start": "2025-06-04", "overlap_end": "2025-06-05", "overlap_workdays": 2} ], "leveled_plan": { "delayed_task_id": "D", "prioritized_task_id": "B", "new_start": "2025-06-09", "new_finish": "2025-06-10", "remaining_float_workdays": 2, "project_finish": "2025-06-17", "added_project_delay_workdays": 0, "resource_conflict_count_after_leveling": 0 }, "memo": "CPM显示关键路径A→C→E→F→G,总工期12个工作日,2025-06-17完成。最早计划中周启在6月4日至5日同时承担B与D,构成唯一资源冲突。按优先级保留B原计划,D推迟至6月9日至10日执行,消耗其5天总浮时中的3天,剩余2天。D新结束日仍早于F最早开始日,项目完工日与工期不变,平衡后无资源冲突。" }